Plan and commit

RACI chart

Also called Responsibility assignment matrix

For each task or decision, agree who is responsible, who is accountable, who is consulted and who is informed.

  • Time30 to 60 minutes
  • People3 to 10 people
  • Steps3

What it's for

Use it when a team keeps tripping over who decides what, or when several teams share one piece of work. The useful part is the arguing: two people who both thought they were accountable find out in the room rather than in a crisis.

Each row should have exactly one accountable person.

How to run it

  1. List the work10 min

    Tasks or decisions down the first column, one per note.

  2. Fill the roles20 min

    For each row, add names under R, A, C and I.

  3. Check the rows10 min

    One A per row. Too many Cs slows everything down. No R means nobody does it.

Tips

  • Keep the notes for one task in a line across the columns, so each row reads left to right.
  • Responsible does the work; accountable answers for it. They can be the same person.

Where it comes from

Responsibility matrices have been used in project management since at least the 1950s. The RACI form has no single known inventor.